Site C Dam Late for Key Milestones Under BC Liberals, Report Reveals

Site C dam construction

B.C. Premier Christy Clark made headlines last month when she claimed that even a few months delay in evicting two Peace Valley families from their homes could add $600 million to the Site C dam project tab.

When Premier designate John Horgan asked BC Hydro to hold off forcing families from their homes this coming week as scheduled, Clark wrote to Horgan that “…with a project of this size and scale, keeping to a tight schedule is critical to delivering a completed project on time and on budget.”

But now BC Hydro’s latest Site C report reveals that — well (Read more…) May’s provincial election and Clark’s headline-grabbing claims — the hydro project was already late meeting three out of eight “key milestones” for 2017 and was at risk of being late for three more.

It begs the question: was Clark trying to deflect blame for Site C construction delays and potential cost overruns onto the soon-to-be NDP government?