BC Hydro’s Bizarre, Multi-Million Dollar Boondoggle to Save Fish from Site C Dam

In a scenario that sounds like something out of a Dr. Seuss book, bull trout and other fish will travel in trucks past the Site C dam for 100 years as part of BC Hydro’s strategy to save the threatened fish species from disappearing from the Peace River.
 
The public hydro provider, which is in the early stages of building the $8.8 billion dam, declined to discuss its fish-saving plans. However, a review of reports filed by the Crown corporation reveals an elaborate and expensive plan that may not work, according to a U.S. fish biologist with bull trout expertise.
 
According to BC Hydro reports, British Columbians will pay approximately $25.5 million to build a “trap and haul” facility for Peace River fish and will spend an additional $1.5 million a year to maintain the facility. The plans are contained in information BC Hydro filed with the Canadian Environmental Assessment Agency.