Decision on Kinder Morgan’s Trans Mountain Oil Pipeline Delayed Until After Next Federal Election

Kinder Morgan pipeline protest

Canada’s National Energy Board (NEB) announced today that it is stopping the clock on the review of Kinder Morgan’s Trans Mountain oil pipeline expansion due to the company’s new proposed corridor through Burnaby, B.C.— which will push a decision on the project back to after the 2015 federal election.

The board will take a seven-month timeout from its 15-month timeline between July 11, 2014, and Februrary 3, 2015, to allow Kinder Morgan time to file studies for its new corridor through Burnaby Mountain, according to a letter to intervenors sent today.

That pushes the board’s deadline to file (Read more…)